3 Stanhope Gate
Client:
Year:
Value:
Contract:
Scope:
Duration:
Stanhope Mayfair Developments Ltd
2025
£12.5M
JCT D&B
New Build / Refurb
2 years
Number 3 Stanhope Gate, just off Park Lane, Mayfair, between Curzon Street and Stanhope Gate comprises a mainly unoccupied early 1900’s, 10 storey concrete and steel framed brick façade Building. CityAxis have been involved with this exciting project for the past five years and recently have been instrumental in the Design and Build of the complete building as a wholepackage, rather than piecemeal packages instructed in the past by the client under a JCT Minor Works umbrella. CityAxis are establishing the principles of fire strategy, working closely with Building Control and Fire Consultants to ensure that all challenges are firmly understood to enable detailed and accurate RIBA Stage 4 drawings to be produced. Such typical challenges involve design of a bespoke fire fighting lift within an existing shaft, individual sprinklering to all floors, compartmentation of commercial areas. Stair lobbies to all levels to avoid stair pressurisation systems. Fire treatment of penthouse triplex both eternal and internal. Fully bespoke MEP systems to all levels. The works are scheduled to be completed in circa eighteen months.
Works included:
-
Full building Strip Out: basement to eighth level, less privately occupied 5th level
-
Full scaffold erection including 40 metre clear span, weather proof top hat and Monoflex wrap throughout.
-
Installation of 1st floor gantry and seven storey height one ton hoist
-
Construction of 2 x eight storey brickwork lightwell infills
-
Construction of 3 x storey luxury residential triplex appartment
-
Ordering of 2 x specialist lifts: 8 storey main fire lift, 3 storey penthouse platform lift
-
Reglazing of both eight storey facades
-
Installation of stone surrounds to all new windows on both facades
-
Full replacement from eighth to basement level, all gutters, gulleys rainwater down pipe
Key Challenges:
-
Stripping a 10 storey building while one floor (5th) in full occupation
-
Comprehensive "waste away" management as no available external space for skips
-
Comprehensive material ingress management as no available external storage space
-
Comprehensive management of site operatives to maintain efficiency within a 10 storey building
-
Detailed survey and investigation of all MEP services prior to strip out
-
Detailed investigation and strip out within existing live lift shaft to maximise new lift cabin size
-
Major structural reinforcement works on upper floors to support Triplex
-
Full asbestos strip out to building including occupied residential 5th floor level